Balance of plant contracts will complete construction of the dam’s generating station and spillways, along with other related facilities.

Alaska Highway News

SiteC-powerhousenearcompletion-oct2021
The Site C powerhouse operations building is nearing completion, October 2021.BC Hydro

BC Hydro says it has awarded four contracts worth $181.5 million for the remaining balance of plant work at Site C dam.

The utility said Thursday the contracts will complete construction of the dam’s generating station and spillways, and other related facilities.

“With these awards, the procurement process for all six balance of plant contracts for the Site C project is complete,” BC Hydro said in the release.

Three of the contracts were awarded to Nanaimo-based F&M Installations Ltd., and the other was awarded to Aecon-Flatiron-Dragados-EBC (AFDE) Partnership.

According to BC Hydro, the four contracts include:

The AFDE Partnership is building the generating station and spillways civil works portion. F&M Installations was previously selected to build the Site C substation.